Evaluation of an Emergency Department Lean Process Improvement Program to reduce length of stay

Background

In recent years, Lean principles have been applied to improve wait times in the Emergency Department (ED). In 2009, an ED Process Improvement Program based on Lean methods was introduced in Ontario as part of a broad strategy to reduce ED length of stay (LOS) and improve patient flow. This study sought to determine the effect of this program on ED wait times and quality of care.

Methods

We conducted a retrospective cohort study of all ED visits at program and control sites over 3 program waves from April 1, 2007 to June 30, 2011 in Ontario, Canada. Time series analyses of outcomes before and after the program and difference-in-differences analyses comparing changes in program sites with control sites were conducted.

Results

In before-after models among program sites alone, 90th percentile ED LOS did not change in Wave 1 (-14 minutes [95% CI -47, 20]) but decreased after Wave 2 (-87 [95% CI -108, -66]) and Wave 3 (-33 [95% CI -50, -17]); median ED LOS decreased after Wave 1 (-18 [95% CI -24, -12]), Wave 2 (-23 [95% CI -27, -19]), and Wave 3 (-15 [95% CI -18, -12]); in all Waves, decreases were observed in time to physician assessment, left without being seen rates, and 72-hour ED revisit rates. In the difference-in-difference models, where changes in program sites were compared with controls, the program was associated with no change in the 90th percentile ED LOS in Wave 2 (17 [95% CI -0.2, 33]) and increases in Wave1 (23 [95% CI 0.9, 45] and Wave 3 (31 [95% CI 10, 51]); modest reductions in median ED LOS in Waves 2 and 3 alone; and a decrease in time to physician assessment in Wave 3 alone.

Conclusions

Although the program reduced ED waiting times, it appeared that its benefits were diminished or disappeared when compared with control sites, which were exposed to system-wide initiatives such as public reporting and pay-for-performance. This study suggests that further evaluation of the effectiveness of Lean methods in the ED is warranted before widespread implementation.

Author information

Authors and Affiliations

Authors

Rights and permissions

Open Access  This article is licensed under a Creative Commons Attribution 4.0 International License, which permits use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons licence, and indicate if changes were made.

The images or other third party material in this article are included in the article’s Creative Commons licence, unless indicated otherwise in a credit line to the material. If material is not included in the article’s Creative Commons licence and your intended use is not permitted by statutory regulation or exceeds the permitted use, you will need to obtain permission directly from the copyright holder.

To view a copy of this licence, visit https://creativecommons.org/licenses/by/4.0/.

The Creative Commons Public Domain Dedication waiver (https://creativecommons.org/publicdomain/zero/1.0/) applies to the data made available in this article, unless otherwise stated in a credit line to the data.

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Vermeulen, M., Stukel, T., Guttmann, A. et al. Evaluation of an Emergency Department Lean Process Improvement Program to reduce length of stay. BMC Health Serv Res 14 (Suppl 2), P110 (2014). https://0-doi-org.brum.beds.ac.uk/10.1186/1472-6963-14-S2-P110

Download citation

  • Published:

  • DOI: https://0-doi-org.brum.beds.ac.uk/10.1186/1472-6963-14-S2-P110

Keywords